The Town of Richmond Sanitary District #1
is a wastewater collection system and wastewater treatment plant (WWTP) originally installed in 1972 to serve the residents and businesses in Boardman. The District is governed by a three member commission appointed by the town board.
Click to view Facility Plan 2023
Rate Increase Letter Sept 2024
Bid Contract awarded - click to view
Wastewater Sources:
20 Single Family Residential Homes
One Apartment Building
Two Bars/Restaurants
Town Hall
Current compliance schedule:
12/31/2023 – Plans and Specifications
• Influent and effluent flow meters
• Repair of leaking stabilization pond
7/1/2024 – Installation Start Date
• Influent and effluent flow meters
9/30/2024 – Installation Completion
• Influent and effluent flow meters
12/31/2024 – Construction Upgrade Progress Report
• Repair of leaking stabilization pond
6/30/2025 – Plans and Specifications
• Repair of leaking stabilization pond
9/30/2025 – Contract Award
• Repair of leaking stabilization pond
6/1/2026 – Construction Start
• Repair of leaking stabilization pond
10/31/2026 – Construction Completion
• Repair of leaking stabilization pond
Upcoming public meetings:
Note: Meetings are the second Monday of the month.
All meetings are scheduled for 6:00 pm at the Town Hall
September 9, 2024
October 14, 2024
November 11, 2024
December 9, 2024
See Agendas and Minutes HERE
Richmond Sanitary District #1 Commissioners
Melissa Meschke - President
[email protected]
Mary Place - Treasurer
[email protected]
Dan Weber - Secretary
[email protected]